No traffic interruptions for Super•Cor heavy haul road arch installation

Heavy haul road arch system at Nammuldi Mine, Australia Live rail lines keep running during construction of arches.

When Atlantic Civil Products Pty Ltd, a major AIL Group licensee in Australian, needed to convince a client that a large, two-lane heavy haul road arch system could be constructed over an existing twin track rail line and two adjacent access roads without traffic interruption. The two compelling factors that sealed the deal were:

  • Our Group's extensive experience designing Super•Cor deep corrugated steel plate structures for use under extreme live loads, and
  • Our project history building the Stockton, UK, railway arches under similar traffic constraints.
No traffic interruption  during installationof heavy haul road arch

Accelerated delivery plus some bells and whistles.

The project specified that the components be delivered and assembled according to a very tight schedule and include imbedded electronic monitoring. AIL got to work, and less than a month after the contract was awarded, the components were manufactured, test assembled and shipped from AIL’s New Brunswick plant to Australia, arriving well ahead of the planned summer construction window.

The first road tunnel went up in seven days, while the subsequent rail tunnel took 18 days and the second road tunnel only 11 days. Engineered ramping and backfilling of approximately 80,000 m3 (2,825,173 ft3) of earthworks took 38 days.  The design incorporated the installation of strain gauges, pressure plates and a data logger to the exterior of the rail tunnel.

There was no rail or road traffic interruption, and the work was completed on time, making for one very satisfied customer.


» Learn more about Super•Cor Steel Structural Plate

Mining-badge

The AIL Group is big on mining!


AIL MINING have been supporting the most successful mine sites for over 40 years.

» Visit our mining website

AIL Vehicular Bridges for Accelerated Construction brochure
 

Check out our Super•Cor brochure

» Download the brochure